Started — · jose@noxus.ai · last activity 2d ago

Linear Granola
No start date, so neither commitment is being measured — this account’s “0 missed” means nobody is counting, not that nothing is late.

Where this stands

vicente@noxus.ai · 2d ago

Status: The project is in progress. The infrastructure deployment is complete, but the 'A-to-Be ticket triage' use case is in UAT and stalled by customer-side blockers.
Shipped (last 7 days):

  • Brisa set up the FQDN / domain for the new deployment (DEP-287).

In progress:

  • Email Rodrigo Carvalheira our position on logging, patch management, and other topics for the DTS review (DEP-672).
  • Prepare action points for Jorge's meeting with Pedro Mota to discuss blockers (DEP-606).

Blocked:

  • The task to run the Golden Set of tickets for customer review is blocked (DEP-446).
  • Waiting on Ricardo Marques Fernandes for his verdict on the Golden Set results to close acceptance tests (DEP-603).
  • Waiting on Brisa for production credentials for Jira (DEP-214).

Next milestone: Go-live for "Use case · A-to-Be ticket triage & backlog management" (no date agreed).

Auto-updated from Linear on 2026-10-23.

Relationship

Linked deployments1 linked
Brisasaas

Health

62At risk
Baseline estimate100
Renewal at risk — perceived instability (high risk)-10
3 open blockers-20
1 breached track SLA-8
Effective health62

Estimate set 14d ago by vicente@noxus.ai

Commitments

counted from the start date
Functional deploymentno start date
First use case liveno start date
Deploy within (days)
Live within (days)

Changes to these commitments

  • Go-live date — Infrastructure deployment unset → 2026-09-02 · 31 Aug 2026 · jose@noxus.ai

Deployments

Current cycle. These are the license organizations that roll up to this customer.

DeploymentVersionAI OpsCapacityMoMOverageToken $Tenants
Brisasaas—2K1.1%+7.7%—$0.38—

Next actions

Nothing outstanding on our side.

No actions recorded.

Blocked on

3 open · 2 past the date we needed them by

SSO / platform access for real-ticket testinghighCustomeroverdue

[Linear DEP-214 · 2ba18584] Connecting the triage use case to the production Jira instance.

Waiting on Brisa · A-to-Be ticket triage & backlog management · raised 28 Aug 2026 (59d ago) · needed by 21 Oct 2026

Close acceptance tests of the triage pipelinehighCustomeroverdue

[Linear DEP-603 · b3745a54] To move the triage pipeline deployment to production.

Waiting on Ricardo Marques Fernandes · A-to-Be ticket triage & backlog management · raised 20 Oct 2026 (6d ago) · needed by 22 Oct 2026

Run of Golden Set tickets for customer reviewmediumCustomer

[Linear DEP-446 · 50ea14dd] Customer validation of the triage pipeline's performance.

Waiting on Ricardo Marques Fernandes · raised 11 Oct 2026 (15d ago) · needed by 28 Oct 2026

Decision on models, FQDN, and SSOhighCustomer

[Linear DEP-332 · 845cbcc8] Unblocking multiple infrastructure and access setup tasks.

Waiting on Pedro Mota (Brisa) · raised 11 Oct 2026 (15d ago) · needed by 12 Oct 2026

FQDN / domain setup for the new deploymenthighCustomer

[Linear DEP-287 · 74eb4cd6] Making the new deployment accessible via its public domain.

Waiting on Brisa · raised 11 Oct 2026 (15d ago) · needed by 20 Oct 2026

Tracks

Use cases, infra deployment and process transformation — each with its own stage timeline and SLA

Infrastructure deploymentInfra deploymentin production

Getting a working deployment in place.

In Production since 27 Aug 2026
A-to-Be ticket triage & backlog managementUse case39d over

L1 triage, L2/L3 escalation routing, duplicate detection and Jira backlog integration for A-to-Be support. Weeks blocked on SSO (Brisa DTS team); server restarted 24 Aug for PostgreSQL extension, access expected 25 Aug. Next: validate flow with Ricardo Fernandes and connect to Jira backlog.

In UAT since 28 Aug 2026stage: 39d overto production: 60d leftChampion: Rodrigo Carvalheira, Brisa lead

Key people

4 active

Rodrigo CarvalheiraChampionprimary

no title · rodrigo.carvalheira@brisa.pt

Most engaged; escalates internally; direct WhatsApp contact.

João GonçalvesSponsor

no title · joao.goncalves@brisa.pt

Perceives the platform as unstable (3 historical incidents); key voice in contract renewal.

Ricardo Marques FernandesTechnical

A-to-Be — key technical tester · ricardo.fernandes@a-to-be.com

Stanley Ramalho LimaOther

Devoteam — implementation partner · dvt_slima@brisa.pt

Tickets

Linked, but Linear files no issues under this customer.

No tickets.

Risks

What could still go wrong. Open risks subtract from health — less than a penalty, because they haven't happened yet.

high

Renewal at risk — perceived instability

João Gonçalves perceives the platform as unstable after 3 incidents; renewal being discussed with a price-freeze clause.

Mitigation: Get the ticket flow validated with Ricardo and connected to Jira quickly to show value before renewal.

jose@noxus.ai · logged 2mo ago

Meeting notes

Pulled from Granola and filed here by attendee domain. Read-only — edit them in Granola.

No meetings filed here yet. Set the customer's email domains above and they arrive on the next sync.

Decks & documents

Everything we have sent this customer. Links only — the file stays where it lives.

Nothing attached yet.

Notes

Context, commitments, gotchas — anything without a field of its own. Claude reads and writes these over MCP; pinned notes come first.

⌘↵ to save

Weekly 11 Set 2026 — Brisa. Feito: Container Apps instalado no offshore Zost, registo ANS enviado, ligação ao Azure OpenAI pronta. Em curso: acesso aos containers para exportar fluxos, validação do Confluence, classificação e restantes itens. Sessão de testes a 10 Set, 14:30-16:00. Bloqueios: serviço restante do domínio noxus.brisa.pt na DTS, com o Rodrigo a pressionar no status das 17:00; Foundry pode atrasar por restrições de VNet e subnet; falta ambiente para testar Confluence à velocidade de produção. UAT fecha 18 Set.

2mo agojose@noxus.aivia MCP

Only missing public domain configuration. Lourenço chased on Saturday Aug 30, waiting on response. Will chase on wednesday if no response

2mo agojose@noxus.ai

Penalties

Incidents held against the account. Open ones subtract from health; resolved ones decay over 90 days.

No penalties logged.

Timeline

Stage transitions, newest first

28 Aug 2026A-to-Be ticket triage & backlog managementstarted at UATvia MCP jose@noxus.ai
27 Aug 2026Infrastructure deploymentNot started → Production· Backfill: account is live and consuming. Date is record creation, not actual go-live.via MCP jorge@noxus.ai
27 Aug 2026Infrastructure deploymentstarted at Not started jorge@noxus.ai